ROAD & PAVEMENT CONSTRUCTION

 

West Thebarton and Phillips Street, Road Reconstruction

Client: City of West Torrens
Construction Period:
 47 Weeks
Value:
$5,700,000

Project Scope:
With such large works having to be undertaken, this project was broken down into two stages. The first stage took place on West Thebarton Road, Thebarton with the upgrade of the road and associated streetscape works. Stage 2 was on Phillips Street taking the upgrade from South Road to Port Road.

The project scope included detailed service investigation and survey, environmental soil classification, installation of 1500m of directional drilled common service trench, kerb removal and replacement, adjustment of existing service pits, footpath reconstruction with new block paving, exposed aggregate concrete driveways, stormwater works (including construction of approximately 500m of stormwater drainage works, up to 4.5m deep), deep lift pavement reconstruction, block paved side street intersections, irrigation and electrical design and installation, soft landscape works and ancillary landscape structures.

Problem Solving: Service locating and potholing prior to construction of new stormwater allowed us to redesign the stormwater to optimise trench excavation and identify service clashes not picked up in original design. This significantly reduced construction cost, unexpected delays due to service clashes and time to install.

Work, Health and Safety:Two-way and pedestrian traffic was successfully managed with site personnel and traffic controllers while works onsite were being undertaken.

Local Resources: This project utilised the services of two local subcontractors, Space Landscape Construction and Consolidated Landscape Services.

 

Birmingham Street Road Reconstruction, Mile End

Client: City of West Torrens
Construction Period:
 10 Weeks
Value:
$775,000

Project Scope:
 Camco were engaged by council to reconstruct 500m of exiting road and road reserve in Birmingham Street Mile End. The project scope included demolition of existing concrete kerbing and footpaths, new base preparation, concrete works, drainage modifications, block paving, profiling of existing pavement materials, deep lift asphalt pavement and associated linemarking. Council requested an additional 525m2 area of road be reconstructed as a variation to the contract which Camco were able to deliver. The profiling and bitumen works were carried out on the weekend and after normal work hours to avoid disruption to businesses in the street.

Innovation: Camco were able to construct the works with minimal disruption to businesses on the road, particularly Premier Stateline Bus service who were able to remain open via a temporary driveway crossover and staged works.

 

Cambridge Terrace Roundabout Upgrade, Unley

Client: City of Unley
Construction Period:
 8 Weeks
Value:
$330,000

Project Scope: 
The scope of this project involved the reconstruction of two roundabouts along Cambridge Terrace to increase safety for cyclists and pedestrians. DDA compliant kerb ramps and openings in the kerb protuberances and splitter islands were also included to provide increased safety for pedestrians. Both Wattle St and Fisher St are busy shortcut routes through the Malvern area. Maintaining traffic flow through the intersections whilst completing the works was a critical criteria for the client. By using temporary traffic signals, we were able to achieve this, and open the intersections to two-way traffic out of hours to avoid any further risks.

Innovation: By utilising pavement profiling techniques and adding additional resources during critical tasks, we were able to optimize the program and complete works within tight timeframes resulting in less disruptions to normal traffic flows.

 

Birdwood High School, Bitumen Hardplay and Landscaping Renewal

Client: Spotless Services
Construction Period: 12 Weeks
Value: $380,000

Project Scope: Upgrade of all hard and soft landscape surfaces within the Birdwood High School exterior. The project scope includes demolition of existing pavements, detailed excavation, granular pavement preparation, concrete kerbing, miscellaneous drainage works, block retaining walls, block paving, irrigation, turfing, mulching and planting. 

Value added options: 
Problem Solving: